If work is due in or around a NUZ distributor, the following applies:
Timetable overview:
Lead time | Action |
---|---|
(min. 3 months) | Planning extensions of the UKV |
min. 4 weeks | Coordination of the work with the staff unit "Coordination IT and Construction |
min. 2 weeks | Arrangement Cleaning, arrangement Moving to temporary power supply, arrangement Decommissioning Ventilation/cooling |
min. 1 week | Notification of planned interruption of power supply |
subsequently, as soon as possible | Communication of reasons for unplanned interruption of power supply |
If you have any questions, please contact the staff unit "Coordination IT and Construction" of the IT Infrastructure Department of the Central IT. Contact: itundbau@zi.uzh.ch.
* NUZ: Network University of Zurich